Which of the following is NOT a part of the operational cycle?

Enhance your skills with the CIPS Procurement and Supply Environments Test. Ideal for procurement professionals, boost your understanding with interactive questions and detailed explanations. Prepare efficiently for success!

The operational cycle in procurement typically includes the key stages of need identification, ordering, and delivery. Each of these stages plays a crucial role in ensuring that goods or services are effectively acquired to meet organizational requirements.

The stage of "need" refers to the process of recognizing and defining what needs to be procured, which is a fundamental starting point. The "order" stage involves placing an order for the required goods or services based on the identified need. The "deliver" stage encompasses receiving the goods or services and ensuring they are delivered as per the agreed terms.

"Negotiate" does not fit into the traditional operational cycle. While negotiation is an important process in procurement, typically occurring before or during the order stage, it is not considered part of the operational cycle itself. Instead, negotiation focuses on terms of supply, pricing, and conditions, which happens as part of contract management but is not a phase of operational execution in the cycle.

Thus, the correct choice is that negotiation is not categorized as part of the operational cycle.